Public Facilities Projects

Operations Center Expansion

  • Phase:

  • Cost: $27.4 million

  • Description: Expansion of Wake Forest Operations Center

  • March 2018 Update

    • Feasibility study completed

Renaissance Centre Renovations Phase 1 & 2

  • Phase: Under construction

  • Cost: $1.237 million

  • Description: Upgrade and renovate areas to improve ability to satisfy the needs of different users/visitors

  • March 2018 Update

    • Construction is 80% complete

  • Renaissance Centre website

Security Systems for Flaherty Park Community Center, Holding Park Community House & Parks, Recreation & Cultural Resources

  •  Phase: Not started
  • Cost: $137,500

  • Description: Install security alarms and cameras, plus card access

  • March 2018 Update

    • Installation will be complete prior to June 2018

 

Northern Wake Senior Center Expansion, plus HVAC and Roof Replacement

  • Phase: Design

  • Cost: $4 million

  • Description: Add exercise and multi-purpose rooms, and replace the roof

  • March 2018 Update

    • Contractors have been pre-qualified and Bid advertisement has been placed (re-advertised due to lack of response to pre-qualifiations). Working with State DEQ to obtain Erosion Control permit.