Proposed Roadway Connections Project

 
ROW/Acquisition
August 2022
Design - 30/60
March 2022
Final Plan Review 90
October 2023
Construction
June 2025

Overview

The purpose of this proposed project is to construct roadway connections in roads that have missing sections which will allow for faster response time for Fire and EMS in case of an emergency, as well as create alternate routes for traffic due to better connectivity.

The following intersections/sections of roadway are expected to be included in this project:

  • South Allen Road - (a 0.02 mile section between Middle Bridge Road and Quail Avenue)

  • Song Sparrow Road (a 0.02 mile section between Trawden Drive and Redstart Court)

  • Pineview Drive (Woodland Drive to Dacus Place) -0.15 mil

  • South Wingate Street (a 0.04 mile section between West Holding Avenue and Kinvara Court)

  • South Wingate Street (West Pine Avenue to West Juniper Avenue) - 0.21 miles

Staff Contact

Joe Guckavan, PE
919-435-9439