Asset Maintenance Projects

Annual Street Maintenance plus Owen Avenue Parking Lot

  • Phase: Construction

  • Cost: $4.367 million

  • Description: Pavement rehab and annual maintenance; pave Owen Avenue parking lot

  • June 2018 Update

    • Contract began in April

Ailey Young Dam Removal & Stream Repair

  • Current Phase: Design

  • Cost: $643,100

  • Description: Remove pond dam and repair stream

  • September 2018 Update

    • All grants approved for design and construction

    • Design is at 75%

    • Permits are obtained or under review

    • Construction to start late fall 2018 and be complete by spring 2019

Flaherty Park Dam Maintenance & Repair

  • Phase: Design

  • Cost: $1.197 million

  • Description: Add riser structure to pond, add parapet wall, flatten slope from 2:1 to 3:1, and upgrade greenway trail from 8 feet wide to 10 feet wide

  • September 2018 Update

    • Project is at 90% design

    • Permits are under review

    • Construction planned for FY 2019-2020

Sanford Creek Greenway Boardwalk Replacement

  • Phase: Not started

  • Cost: $4.664 million

  • Description: Redesign and replacement of boardwalk due to age and changing environmental conditions.

  • September 2018 Update

    • Redesign fall 2021 and reconstruct in 2022-2023

Wake Forest Reservoir Improvements

  • Phase: Design

  • Cost: $4.7 million

  • Description: Dam Improvements, G.G. Hill Water Treatment Plant demolition, Phase I-upgrade parking lot, boat ramp, dock and bridges, Phase II- Oak Grove Church Road trail bridge and continuation of soft trail on east side of reservoir

  • September 2018 Update

    • Coordinating transfer of property from City of Raleigh to Town of Wake Forest

Transportation Sidewalk

  • Phase: Ongoing

  • Cost: $75,000

Sidewalk Replacement

  • Phase: Construction

  • Cost: $75,000

  • Description: Replace deteriorated, broken and/or uneven sidewalks

 

Richland Creek Stream Restoration

  • Phase: Design is complete, Construction will begin in fall 2018

  • Cost: $8,600 design, $75,000 construction

  • Description: Repair approximately 100 LF of stream bank due to damage from Hurricane Matthew

  • September 2018 Update

    • Design is complete

    • Permits are approved

    • Construction scheduled to begin in November 2018 and completed by December 31, 2018

Smith Creek Soccer Center Improvements

  • Phase: Not Started

  • Cost: $1.3 million

  • Description: Restroom facilities, repave parking lot, add greenway loop, add trees, upgrade playground facilities, add environmental education stations

North Main Stormwater Repair & Roadway Rehabilitation

  • Phase: Design

  • Cost: $18,790

  • Description: Relocate and replace failing stormwater pipe and box between North Main St., N. College St. and N. Wingate St. Upgrade existing boxes on North Main Street (US1A) to current standards with hood and grade, re-granite curb as needed, and resurface street to minimize flooding.

  • June 2018 Update

    • Preliminary design is underway

Asset Maintenance Projects
Assistant to the Town Manager
919-435-9513