- Nov. 13, 2018Bid advertisementCompleted: Nov 13, 2018
- Dec. 13, 2018Bid packages dueCompleted: Dec 13, 2018
- Jan. 15, 2019Bid awardedCompleted: Jan 15, 2019
- Feb. 4, 2019Work begins along S White St
As part of the Capital Improvement Plan, the Town of Wake Forest Board of Commissioners approved funds to continue implementing the Renaissance Plan for Downtown Wake Forest.
Downtown Improvements, Phase 3 consists of street and landscape improvements along Sections 1 – South White Street: East Holding Avenue to Elm Avenue and 2A – East Owen Avenue: South White Street to Brooks Street.
The Town completed South White Street, Phase 1: Jones Avenue to Roosevelt Avenue (NC 98 Business) in 2010 and South White Street, Phase 2: Elm Avenue to Spring Avenue in 2012.
Staff Contact
Candace Davis
Assistant to the Town Manager
919-435-9513
Design Engineer/Construction Administration
PE Kimley-Horn & Associates
Jason Pace
919-667-2135 (office)
919-600-4511 (cell)
Construction Contractor
State Contracting, Inc
Rob Todd
919-453-2755 (office)
919-538-8452 (cell)
Project Superintendent
Billy Sowers
919-453-2755 (office)
919-397-5431 (cell)
Construction Inspector
Mott MacDonald
Al Jones
984-220-2038 (cell)