Town offers update on South Franklin Street Widening Project
Wake Forest officials say progress continues on the South Franklin Street Widening Project with recent approvals clearing the way for the next phases of construction, including:
Streetlight Enhancements: Wake Electric will soon install decorative streetlight poles that will improve roadway lighting and match upgrades along other sections of the corridor.
Utility Revisions: Plan revisions that address dry utility conflicts have been approved, and the contractor has been authorized to move forward.
Retaining Wall Adjustment: A previously identified conflict with underground electrical infrastructure has been resolved allowing retaining construction of the retaining wall to proceed.
Lane Closures: Intermittent lane closures will occur throughout the project. These are weather-dependent and will be coordinated to reduce impacts on traffic.
In addition, the following work is scheduled to begin in the coming weeks:
Pipe crews will return the week of May 26.
Wall construction will begin the week of June 2.
Roadway work is anticipated to begin in mid-June, contingent on progress by utility providers.
Meanwhile, grading, concrete work, storm drainage installation, and multi-use path (MUP) construction will continue.
Officials say substantial completion of the project is scheduled for the end of September 2025 with final completion expected in late October/early November.
The Town of Wake Forest appreciates the community’s continued patience and cooperation. The South Franklin Street Widening Project remains a key investment in Wake Forest’s transportation infrastructure, and the Town is committed to keeping the community informed as progress moves forward. For more information, visit https://bit.ly/SFranklinWideningProject or email CIP Manager Steve Meyer at smeyer@wakeforestnc.gov.