Rogers Road Grade Separation Project Update

Member for

7 years 10 months
November 20, 2026

On Wednesday, Nov. 18, NCDOT shared the following update about the NCDOT Rogers Road Grade Separation project:

Blythe Construction, based in Charlotte, has been selected as the contractor for the project. Construction is anticipated to begin after the new year.

Many of you have reached out with questions about how traffic will be managed during construction. An on-site detour will be provided throughout the project to maintain access to all locations along both sides of Rogers Road.

Construction will take place in phases, and the detour will adjust as work progresses. We are currently adding maps to our project website at https://ncdot.publicinput.com/h1768 that will show the detour routes for each phase.

The work you see taking place now is utility work. If any work requires a significant traffic impact, we will make sure you hear about it from us first. We appreciate your patience as we move forward with this project and will continue to keep you informed.

For more information and to sign up for updates, visit https://ncdot.publicinput.com/h1768