On Friday, Nov. 20, NCDOT shared the following update about the Capital Boulevard/US 1 North Upgrade (Raleigh to Wake Forest):
The Capital Boulevard project continues moving forward, with geotechnical work, design, and property acquisitions underway as the NC Department of Transportation prepares for future construction.
NCDOT continues to coordinate with the Town of Wake Forest and City of Raleigh to refine the project designs. Segments A and B, which extend from I-540 to north of Burlington Mills Road, are in the final design process, and right-of-way acquisition has begun. Segments C and D are expected to enter the final design phase soon.
Several design revisions have been made through this ongoing coordination, including changes to roadway alignments, driveway locations, intersections, and utility and drainage easements. One of the most significant updates involves the Burlington Mills Road interchange. You can view those changes by visiting our project page at https://publicinput.com/Capital-Boulevard-Upgrade.
Burlington Mills Road Interchange
NCDOT previously recommended a diamond interchange at Burlington Mills Road and U.S. 1 (Capital Boulevard). However, continued coordination with the Town of Wake Forest resulted in a revised layout that better meets the area's needs. The current design proposes a partial cloverleaf interchange that will provide access in all directions along Burlington Mills Road and U.S. 1 (Capital Boulevard).
Geotechnical work in Segments A and B has been underway since early summer. Additional soil and pavement testing is also taking place along one of the planned service roads. Roadway plans have advanced to the point where utility and drainage work can begin.
Project Segments
The project is divided into four sections:
• Segment A: Capital Boulevard from I-540 to Durant Road.
• Segment B: Durant Road to Burlington Mills Road.
• Segment C: Burlington Mills Road to the N.C. 98 Bypass.
• Segment D: The N.C. 98 Bypass to Purnell Road/Harris Road.
Right-of-Way Acquisition & Construction Timeline
Property acquisition is underway for Segments A and B. This process involves purchasing the property needed to build the project. Property owners will be contacted as the project progresses, but it could be several years before some hear from an NCDOT right-of-way agent. The acquisition process is expected to take approximately five years.
Construction on Segments A and B is currently scheduled to begin in 2031.
For more information and to sign up for updates, visit https://publicinput.com/Capital-Boulevard-Upgrade.