Stadium Drive Complete Street Project

Overview 
The Town of Wake Forest is implementing a Complete Street vision along Stadium Drive (SR 1930) from Capital Boulevard (US-1) to North Wingate Street (SR 1954). This will improve both vehicle and pedestrian safety as well as traffic flow. Work began in spring 2018 and is anticipated to be completed by winter 2019.


Improvements
The typical section includes three lanes with curb and gutter, left-turn lanes at intersections and driveways, a 10-ft wide multi-use path on the south side, five-ft wide sidewalks on the north side, wide striped shoulders on each side of the roadway, a pedestrian refuge island, high visibility crosswalks and ramps, and accessible transit stops.

 

September 2018 Update

  • Curb is being installed from Glenco Drive to McDowell Drive on the south side
  • Waterline and sanitary sewer work is 75% complete
  • Major utilities are being relocated from bridge east to N. Wingate Street
  • SEBTS parking lots are installed near Judson Drive
  • Fill and grading has begun for retaining wall west of Judson Drive 

 

Project Schedule

2012 Town secured $300,000 STP-DA grant from the Locally Administered Projects Program (LAPP)
April 2013 Town received funding authorization from NCDOT to begin design
2015 Design completed
June 2015

Town secured $3.3 million STP-DA grant from the Locally Administered Projects Program (LAPP) to support right-of-way acquisition and construction

September 27, 2017 Construction Authorization Approved by NCDOT
December 19, 2017 Town of Wake Forest Board of Commission Approves Resolution for Construction Contract
April 2018 Start of Construction

Late 2019

Anticipated Project Completion