Public Works Projects

Line Construction/System Improvements

Phase: Ongoing

Cost: $775,000

Description: Extend and upgrade the electrical distribution system

Update: Annual initiative - reviewed on a yearly basis


RF Load Management Thermostats

Phase: Not started

Cost: $40,000

Description: Install RF Thermostats to complete the RF Load Management Project

Update: Project is in test pilot mode due to a software issue by Landis + Gear. Pilot numbers have been installed.


Town Roadway Lighting

Phase: Ongoing

Cost: $30,000

Description: Lighting Town roadways according to NCDOT and ASHTO standards

Update: Annual project funded in FY 2017-18 budget