UNPAVED ROADS PROJECT

The Town of Wake Forest will begin construction on the following unpaved roads on June 20: Mangum Lane, Carter Street, Farm Road, Farm Ridge Road, Spring Valley Road, Highland Avenue, and Walnut Avenue starting mid-June 2011.

Below is the tentative work schedule:

Location

Anticipated Start Date

Anticipated Completion Date

Mangum Lane

6/20/11

10/13/11

Carter Street

7/6/11

10/14/11

Farm Road

7/8/11

10/18/11

Farm Ridge Road

7/8/11

10/19/11

Spring Valley Road

8/24/11

10/21/11

Highland Avenue

9/8/11

10/24/11

Walnut Avenue

9/26/11

10/25/11

 

Additional information will be provided as it becomes available concerning the project schedule, progress, and any anticipated delays.