The Town of Wake Forest will begin construction on the following unpaved roads on June 20: Mangum Lane, Carter Street, Farm Road, Farm Ridge Road, Spring Valley Road, Highland Avenue, and Walnut Avenue starting mid-June 2011.
Below is the tentative work schedule:
| Location |
Anticipated Start Date
|
Anticipated Completion Date
|
| Mangum Lane |
6/20/11
|
10/13/11
|
| Carter Street |
7/6/11
|
10/14/11
|
| Farm Road |
7/8/11
|
10/18/11
|
| Farm Ridge Road |
7/8/11
|
10/19/11
|
| Spring Valley Road |
8/24/11
|
10/21/11
|
| Highland Avenue |
9/8/11
|
10/24/11
|
| Walnut Avenue |
9/26/11
|
10/25/11
|
Additional information will be provided as it becomes available concerning the project schedule, progress, and any anticipated delays.