Road Resurfacing Project

Wake Forest's road rehabilitation and resurfacing project began Aug. 22, 2011. Colder temperatures and seasonal conditions have temporarily postponed the work until March 2012. 

The initiative includes full depth patching, roadway repairs, and repaving. The roads were selected based on their need of repair.

Barnhill Contracting Company was the low bidder with a project cost of $2,758,993.50. 

Street Tentative Start
6th 9/1/2011
Brooks 9/12/2011
Cardinal 8/22/2011
Carmel Woods 3/15/2012
Dacus 10/3/2011
Drogheda 3/15/2012
Elizabeth 9/19/2011
Elmwood 9/28/2011
Evesham 8/29/2011
Fairburn 10/3/2011
Havisham 8/29/2011
Haywicke 3/15/2012
Hogan 3/15/2012
Holding 10/6/2011
Jones 9/5/2011
Julie Ann 9/22/2011
Liberty 3/15/2012
Mocking Bird 8/22/2011
N. Wingate 9/19/2011
Nuthatch 8/22/2011
Palmer 3/15/2012
Pine 9/1/2011
Pine Ridge 9/22/2011
Pine View 10/3/2011
Rayburn 10/10/2011
Sparrow 8/22/2011
Taylor 9/8/2011
Taylor & Cedar 9/8/2011
Tesser 9/28/2011
Tracy 9/28/2011
South White 3/15/2012
Willow Wisp 3/15/2012
Woods Mill 10/6/2011
 

Please be aware of construction crews, follow flagging directions, detours, lane closures, and road closure signage.